  • Incident reduction process flow (Sophia’s offer)

    Process Setup

    Actions

    Phase

    Document

    Responsible

    Regularity

    Proper Resource Allocation

    • PM should add a note to the “Requests” tab in the Workload file about planned start date of the project and its details

    • On the Workload call, PMO should assign proper resources for the project (depends on the devs skills & workload)

    • Team-leads should approve the dev team assigned to the project

    INITIAL SETUP

    PMO / Team-leads

    At the start of each project, with ongoing adjustments as needed

    External Kick-off call

    • External kick-off call should be arranged by PM at the beginning of the project

    • PM & Client should participate on the call (Team-lead could be included if needed)

    • All points discussed on the call should be documented

    DISCOVERY

    Сheck-list for client’s briefing
    SOW

    PM

    At the start of each project

    Internal Kick-off call

    • Internal kick-off call should be arranged by PM at the beginning of the project

    • PM, Dev team, QA, Team-leads should participate on the call

    • PM should be prepared to introduce the project goals & scope, design, client needs to the team

    • Team-leads should make their conclusions about complexity of the functionality: discuss with the team all difficulties which could happen, pick the right methods and make sure FE, BE devs follow TL instructions/vision

    • After all technical details are cleared, the features should be precisely estimated with the whole team, timeline should be created/updated accordingly

    DISCOVERY

    • Project passport

    • Added feature/s development decisions to SOW

    • Updated Timeline

    PM

    At the start of each project

    Estimate

    Project setup

    • PM should make decomposition of the features, all features should be well described (consulted with devs or TL)

    • PM should add issues to the Jira with all estimates and deadlines

    • TL has to make sure project setup correctly with stage/Git/..

    DEVELOPMENT

    Project setup check-list

    PM / Team-leads

    One-time setup, periodic review as needed

    Communication procedures & tracking of the progress

    • PM should conduct daily meetings with the team, checking devs progress, involving and updating TL if needed

    • All decisions / notes discussed on the calls should be documented in the Meeting notes

    • Weekly reporting by Team-leads regarding tech details of the projects where TL was involved to notify management & PMO

    DEVELOPMENT

    • Meeting notes

    • Updated SOW

    • Weekly reports

    PM / Team-leads

    Continuously

    Documenting changes

    • All technical decision changes made by team must be approved by TL

    DEVELOPMENT

    • Updated SOW / Timeline

    PM

    With each change, continuously

    Code review

    • PM should make sure that issues are moving according to the workflow, each page or feature should go through the Code review after its completing

    • TL should review the issue within 1 day after it appears in the code review status

    • Self check by devs

    DEVELOPMENT

    • Conclusions/ common mistakes added to the Performance Review document

    PM / Team-leads

    With each code change, continuously

    QA / Testing

    • QA should test each issue after FE+BE completed

    • Automated testing?

    DEVELOPMENT

    • Test cases

    • Browsers & devices

    With each code change, continuously

    Release procedures

    • Go-live check-list must be divided by FE,BE,PM and checked by TLs before launch

    • Remember about backups

    PRE-LAUNCH

    Go-live check-list

    PM / Team-leads

    Before each release, periodically according to schedule

    Go-live

    LAUNCH

    • Go-live check-list

    • Instructions for devs

    PM / Team-leads

    During each release, periodically according to schedule

    Retrospective

    LAUNCHED

    Retrospective document

    PM

    After each project release

    Performance review

    • Despite of the flow there should be procedures as self-development, review of the team members by the Team-leads

    • Competencies review document for each team member

    • List with dev’s skills

    Team-leads

    Once in 3 months

    Devs Handover

  • Handover Rocken to Andrii

    Date

    Event

    What to do?

    Useful links / notes

    15.05 Wed 11am

    Daily

    • Last status before I go to vacation

    • Introduce the plan for next 2 weeks for the team

    • Motivation speech from Ihor

    Release plan

    16.05 Thur 11am

    Daily

    • Check team’s status

    • Check how much free time left for each team member in the Sprint 69

    • Discuss the tasks left for the Processes (синяя звезда)

    • Create and assign Processes tasks if possible (if not leave them for Sprint 70)

    Tasks left for Processes:
    Filters the same as now without Archived – доробити
    Forecast – зробити
    Search – доробити (


    RT-3871


    RT-3872

    )
    Adding – готово
    Change status – дизайн ін прогрес+дев
    Interview dates negotiation – є дизайн, треба девелопмент
    Listing and collapse – є дизайн, треба девелопмент

    17.05 Fri 11am

    Daily

    • Check team’s status

    • Ask what they plan to finish during Friday and whats left for the next sprint

    • Remind to the team that they should prepare for the demo on Mon

    (синяя звезда)Ask Ihor how the things going with Company bugs

    20.05 Mon 11am

    Daily
    Demo
    Sprint planning

    Daily

    • Check team’s status

    • Ask if they completed what was planned for Friday

    • Ask how much time they need to finish the tasks from Sprint 69 (those will be moved to Sprint 70)

    • Calculate free time for Sprint 70 for each team member

    Demo

    • Ask each team member to show what they did during last sprint

    Sprint planning

    • Add tasks from the file to JIRA

    • Estimate those tasks with the team and pick the assignees

    • Pick the bug hunter for the Sprint 70 (last Bughunter was Dasha, so this time it should be Anton)

    Leave a few days free for the Bughunter, since there could be support tasks which could affect the NA sprint tasks
    But add to the Sprint 71 NA tasks which Bughunter could take if he has a free time

    • Check the tasks we already have in Sprint 70 and set up the priorities, if something is more urgent – leave in this Sprint, other – move to Sprint 71 (синяя звезда)

    • Make sure each time member has a full workload for the Sprint (10 days) and everyone understands what they should do in the assigned tasks

    Check the following existing tasks in Sprint 70 with Julia and Ihor:

    • Open tasks – how urgent it is?

    • Dev blocked tasks on Valya – what should we do with it? what is the real status of each?

    • Bugs – Sprint 70 or post-release?


    (синяя звезда) Ihor should finish by the end of Sprint 69:

    • Company bugs, all tabs tasks, Communication module

    21-23.05 Mon-Thu 11am

    Dailies

    • Check team’s status and make sure everyone & everything goes according to the plan

    • Each team member must say – what they did yesterday / what they plan to do today

    24.05 Fri 11am

    Daily + Half-sprint retro (if needed)

    • Check team’s status and make sure everyone & everything goes according to the plan

    • If you don’t like the progress, connect with Ihor and Julia and plan what you should do to speed up the process

    • Talk with Julia and Ihor (depends on progress) when & how Julia plans to gave the stage link to the Rocken team

    27-30.05 Mon-Thu 11am

    Dailies

    • Check team’s status and make sure everyone & everything goes according to the plan

    31.05 Fri 11am

    Daily + retro

    • I come back (улыбка)

    • Success result: All tasks from the list planned for Sprint 69 + Sprint 70 are done from the dev’s side

  • Weekly report 04.12-08.12

    Project Schedule & Scope Status

    Scope/Projects

    Status

    Deadline

    Budget

    Additional Requests

    Team

    Update

    Estimated

    Spent

    Estimated

    Spent

    ROCKEN

    ON TRACK

    369h

    ROCKEN team

    • Vika&Ivan test CRM/Talent; Dima works on Orders; Sasha worked on Company page connect to API and bugs; Dasha continue working on Applications reports for BI; Anton worked on migrations; Valya works on Vacancy view

    One-Line: Porsche / Harley Davidson (Digital Koala)

    ON TRACK
    (support)

    101h

    Laravel: Slavik Syvyniuk
    Laravel Lead: Yurich
    QA: Ilya Bilyk

    • Working for final requests for Porsche (small tasks)

    • No new requests for Harley Davidson – they are working on the design and finalizing requirements with the client

  • Weekly report 20.11-24.11

    Project Schedule & Scope Status

    Scope/Projects

    Status

    Deadline

    Budget

    Additional Requests

    Team

    Update

    Estimated

    Spent

    Estimated

    Spent

    ROCKEN

    ON TRACK

    1102h

    ROCKEN team

    • Vika&Ivan test CRM/Talent; Dima worked on Chats & Files; Sasha worked on Company page connect to API and bugs; Dasha continue working on reports for BI; Anton worked on migrations; Valya worked on Publication, Vacancy and Process lists

    • Slavik works on stylecloud, didn’t want to interrupt him for now, but will discuss this week with him internally the possibility to start asap

    One-Line: Porsche / Harley Davidson (Digital Koala)

    ON TRACK
    (support)

    98h

    Laravel: Slavik Syvyniuk
    Laravel Lead: Yurich
    QA: Ilya Bilyk

    • Waiting for final requests for Porsche

    • No new requests for Harley Davidson – they are working on the design and finalizing requirements with the client

  • Weekly report 13.11-17.11

    Project Schedule & Scope Status

    Scope/Projects

    Status

    Deadline

    Budget

    Additional Requests

    Team

    Update

    Estimated

    Spent

    Estimated

    Spent

    ROCKEN

    ON TRACK

    824h

    ROCKEN team

    • Vika&Ivan test CRM/Talent; Dima worked on Chats; Sasha worked on Company and Users page connect to API; Dasha works on Paas reports for BI; Anton worked on bugs; Valya worked on Company page and Publication list

    • Completed Questionnary landing

    • Slavik works on stylecloud, didn’t want to interrupt him for now, but will discuss this week with him internally the possibility to start asap

    One-Line: Porsche / Harley Davidson (Digital Koala)

    ON TRACK
    (support)

    98h

    Laravel: Slavik Syvyniuk
    Laravel Lead: Yurich
    QA: Ilya Bilyk

    • Received final requests for Porsche brochures, will work on it this week

    • No new requests for Harley Davidson – they are working on the design and finalizing requirements with the client

  • Weekly report 06.11-10.11

    Project Schedule & Scope Status

    Scope/Projects

    Status

    Deadline

    Budget

    Additional Requests

    Team

    Update

    Estimated

    Spent

    Estimated

    Spent

    ROCKEN

    ON TRACK

    501h

    ROCKEN team

    • Vika&Ivan test CRM/Talent; Dima works on Forget password + Orders; Sasha is working on bug fixing + Company page connect to API; Anton works on bugs and started migrations; Valya worked on CRM Users page

    • Working on second Landing should be finished this week

    • Slavik onboarding plans from the next week

    One-Line: Porsche / Harley Davidson (Digital Koala)

    ON TRACK
    (support)

    98h

    Laravel: Slavik Syvyniuk
    Laravel Lead: Yurich
    QA: Ilya Bilyk

    • Waiting for Porsche approve to transfer changes live, had few minor requests

    • Prepared stage for Harley Davidson

  • Weekly report 30.10-03.11

    Project Schedule & Scope Status

    Scope/Projects

    Status

    Deadline

    Budget

    Additional Requests

    Team

    Update

    Estimated

    Spent

    Estimated

    Spent

    ROCKEN

    ON TRACK

    1508h

    ROCKEN team

    • Vika&Ivan test CRM/Talent; Dima worked on Candidate Interview, Talent Contact Info API; Sasha is working on bug fixing; Anton worked on Localization, Reject & accept actions for Companies and started migrations; Valya works on CRM Users page

    • Had an issue with dev work (Landing) – we didn’t meet the deadline and Rogkov communication was not professional. Landing was published live.

    • Critical issue with sending invitations to real people from stage – had a retro with team, wrote the sum-up to the Rocken dev channel

    One-Line: Porsche / Harley Davidson (Digital Koala)

    ON TRACK
    (support)

    96h

    Laravel: Slavik Syvyniuk
    Laravel Lead: Yurich
    QA: Ilya Bilyk

    • Waiting for Porsche approve to transfer changes live

    • Had a call with Egzon & Danny regarding the Harley Davidson project – they should have final call on 13.11 and start the design after that, in the meantime we will work on preparing stage, copying Porsche, clearing the database

    • Digital Koala is a new name of the OneLine’s brochures product

  • Weekly report 23.10-27.10

    Project Schedule & Scope Status

    Scope/Projects

    Status

    Deadline

    Budget

    Additional Requests

    Team

    Update

    Estimated

    Spent

    Estimated

    Spent

    ROCKEN

    ON TRACK

    1128h

    ROCKEN team

    • Vika is testing Talent; Dima prepared stage for CRM and started with Orders functionality; Sasha is working on bug fixing; Anton is working on enhancing Companies actions; Valya works on CRM Users page

    One-Line: Porsche

    ON TRACK
    (support)

    96h

    Laravel: Slavik Syvyniuk
    Laravel Lead: Yurich
    QA: Ilya Bilyk

    • Waiting for Porsche approve to transfer changes live

  • Weekly report 16.10-20.10

    Project Schedule & Scope Status

    Scope/Projects

    Status

    Deadline

    Budget

    Additional Requests

    Team

    Update

    Estimated

    Spent

    Estimated

    Spent

    ROCKEN

    ON TRACK

    872h

    ROCKEN team

    • Vika is testing Talent; Dima finished CRM Applications & next week will start gathering CRM components on stage; Dasha continue working on BI board (charts connecting FE to BE); Sasha is working on bug fixing; Anton is working on Localization; Valya works on CRM Users page

    • Talent testing from ROCKEN side was finished, Julia added few tasks in the new epic (improvements and bugs)

    • Had a demo call for Toni, updated release date is the end of the year

    One-Line: Porsche

    ON TRACK
    (support)

    96h

    Laravel: Slavik Syvyniuk
    Laravel Lead: Yurich
    QA: Ilya Bilyk

    • Had few minor requests

    • Waiting for Porsche approve to transfer changes live

  • Sophia – Projects to handover [09.10-13.10]

    Project Name + Link to Jira

    Client / People to communicate

    Team

    Communication channel

    Comment / What needs to be done

    Responsible PM

    https://cheitgroup.atlassian.net/jira/software/c/projects/RT/boards/32

    ROCKEN
    Miriam, ROCKEN team

    ROCKEN team

    https://cheitgroup.slack.com/archives/CQU1BV57Z

    • Discussed w/ Julia

    Julia

    https://cheitgroup.atlassian.net/jira/software/c/projects/PRSCH/boards/34

    OneLine
    Egzon, Danny – OneLine / partners

    Slavik Syvyniuk
    Yurich (Lead)

    https://onelinemarketing.slack.com/archives/C02C3NQ44EL


    • PRSCH-122

      ,


      PRSCH-129

      is currently on review from the Client’s side
      Waiting for their feedback

    Andrii

    (синяя звезда) PMO Responsibilities

    Issue

    Details

    Responsible

    Jira administration

    Instructions how to create project – https://cheitgroup.atlassian.net/l/cp/0y1GeHh4

    Slava

    Approve estimates

    Alex

    Problem with resources / Workload issues

    Alec

    Start new project / Go-live issues

    Alex

    Problems with clients (RiefMedia/OneLine)

    Alex

    Assigning projects / tasks to PMs

    Alex

    Approve day-offs in Hurma

    Tanya

    (синяя звезда) PM Plans

    PM

    Tasks

    Actions / Decisions

    Anna

    • Siento – landing ready for review 09.10

    • Analyze spent/estimated time on Siento

    • OneLine – re-audit SEO

    • HeyLocate – 2 new pages (end of the next week)

    • MYCON – go live

    • Shopify project – ask client about price (cooperation with sales team)

    • Presentation for estimation

    Kate

    • Swisskrono – next week go-live

    • Aprico – new project from OneLine

    • SMTP double-check multi language

    • Rosarot requirements in google doc – Discovery phase

    • Saclab – documentation for next year

    • Casinor another project from Dan on Alex

    Nastya

    • RiefMedia – Music&Media fixes, Futures contact page

    • CVshop – waiting for SEO articles (Tuesday)

    • Performance – 26.10 deadline

    Givi

    • BussMurtonLaw – client should pay invoice

    • Hochschule – change link structure + additional week of work

    • New project – need proper design, start new project

    • 2 new estimations waiting for approve

    Andrii

    • Stingray – main animation on the HP

    • Support projects/tasks from OneLine

    • Need better documentation for support projects

    • Problem with resources