Project Schedule & Scope Status
|
Scope/Projects |
Status |
Initial ETA |
Current ETA |
Initial Budget |
Current Budget |
Update |
|---|---|---|---|---|---|---|
|
Project 1 |
ON TRACK |
10/11/21 |
10/11/21 |
100h |
50h |
|
|
Project 2 – Milestone 1 |
WITH RISK |
10/11/21 |
10/15/21 |
100h |
50h |
|
|
Project 2 – Milestone 2 |
DELAYED |
10/08/21 |
10/18/21 |
100h |
50h |
Issues/Risks/Changes:
|
Issues/Risks |
Status |
Impact |
Updates / Action points |
|---|---|---|---|
|
Issue: Missing designs for Phase 2.0 |
RESOLUTION IN PROGRESS |
This will have an impact on the ETA for Phase 2.0 |
Follow up with the customer to provide design ASAP. |
|
Risk: 3rd party library |
HIGH RISK |
This might have an impact on the project timeline |
Do a SPIKE to investigate and update estimation on library implementation |
|
Change Requests: Additional requirements for Phase 2.0 |
EVALUATION IN PROGRESS |
budget increase for 20h |
Confirm budget, timeline and scope changes with the client after evaluation. |