Project Schedule & Scope Status
|
Scope/Projects |
Ticket |
Status |
Opened |
Date of delivery |
Estimation/Budget |
Fact spent |
Asgn |
Comment |
|---|---|---|---|---|---|---|---|---|
|
NUCC |
|
hold |
20.11 |
21.11 |
– |
– |
Kjartan |
I sent an investigation to the client |
|
Total time |
– |
|||||||
|
boa |
|
Done |
28.11 |
30.11 |
– |
Danny Kurasinski |
Bug, won’t be paid for this fix |
|
|
Total time |
2h 43m |
|||||||
|
Casa-Nobile |
|
In progress |
20.11 |
– |
– |
– |
Egzon Cekaj |
related to other task with safepray |
|
|
Done |
20.11 |
– |
– |
1h 0m |
Egzon Cekaj |
Tested new cert |
|
|
Total time |
1h 0m |
|||||||
|
Chiidaspa |
|
Done |
24.11 |
29.11 |
– |
11h 9m |
Danny Kurasinski |
Problems with prices in the checkout |
|
|
Done |
26.11 |
01.12 |
– |
4h 10m |
Danny Kurasinski |
||
|
|
hold |
26.11 |
– |
8-9h |
32m |
Danny Kurasinski |
Wait approving estimation |
|
|
Total time |
16h 3m |
|||||||
|
COBAX |
|
In progress |
30.11 |
– |
– |
2h 1m |
Liliano Tenore |
couldn’t fix, wrote to plugin’s support |
|
|
Done |
14.11 |
27.11 |
– |
45m |
Liliano Tenore |
||
|
|
In progress |
9.11 |
– |
– |
– |
Egzon Cekaj |
changes in form functionality and SMTP |
|
|
|
Done |
27.11 |
30.11 |
– |
45m |
Egzon Cekaj |
||
|
|
Done |
17.11 |
27.11 |
– |
8m |
Egzon Cekaj |
||
|
|
hold |
28.11 |
– |
– |
3m |
Liliano Tenore |
wait info from Liliano, maybe task is not needed |
|
|
Total time |
3h 42m |
|||||||
|
FUJI |
|
In progress |
28.11 |
– |
~8h |
6h 35m |
Severin Bucher |
|
|
|
In progress |
30.11 |
– |
– |
– |
Severin Bucher |
||
|
Total time |
6h 35m |
|||||||
|
FWFO |
|
In progress |
21.11 |
– |
– |
4m |
Severin Bucher |
complicated git flow on client side |
|
Total time |
4m |
|||||||
|
Gefra |
|
In progress |
16.11 |
– |
6-8h |
– |
Severin Bucher |
Approved estimation and can start |
|
Total time: |
– |
|||||||
|
Just.Swiss |
|
In progress |
25.10 |
– |
18-20h |
– |
Danny Kurasinski |
wait approve estimation |
|
|
In progress |
14.11 |
– |
5-6h |
3h 48m |
Danny Kurasinski |
need to fix anchor link |
|
|
Total time: |
3h 48m |
|||||||
|
Rosarot |
|
In progress |
20.11 |
– |
– |
19m |
Egzon Cekaj |
investigated showing all cases |
|
|
In progress |
27.11 |
– |
– |
3m |
Egzon Cekaj |
different design and current styles on a case page |
|
|
Total time |
22m |
|||||||
|
Flyttesiden |
|
In progress |
21.11 |
– |
– |
Mikael |
We have to add some fields to edit texts on front-end part |
|
|
|
In progress |
21.11 |
– |
– |
Mikael |
Changes on checkout steps |
||
|
|
Done |
28.11 |
29.11 |
– |
22m |
|||
|
Total time |
22m |
|||||||
|
Win4Win |
|
In progress |
28.11 |
– |
– |
3h 48m |
Chiara Gragnano |
have to fix mandatory birthday field on mobile |
|
Total time |
3h 48m |
|||||||
|
WSA |
|
In progress |
3.11 |
– |
– |
1h 16m |
Danny Kurasinski |
|
|
|
Done |
28.11 |
29.11 |
– |
1h 31m |
Danny Kurasinski |
||
|
Total time |
2h 48m |
|||||||
|
Auto-Monkey |
|
Done |
29.11 |
01.11 |
– |
2h 7m |
Luca Campanaro |
|
|
Total time |
2h 7m |
|||||||
|
Bluecare |
|
Done |
28.11 |
29.11 |
– |
2h 19m |
Severin Bucher |
|
|
Total time |
2h 19m |
|||||||
|
Kiana |
|
Done |
28.11 |
29.11 |
– |
1h 19m |
Danny Kurasinski |
|
|
Total time |
1h 19m |
|||||||
|
PET |
|
In progress |
28.11 |
– |
– |
2h 31m |
Severin Bucher |
have to fix on other languages |
|
Total time |
2h 31m |
|||||||
|
UST |
|
Done |
31.10 |
29.11 |
3h |
2h 58m |
Kateryna Lytvinchova |
|
|
Total time |
2h 58m |
|||||||
|
Total support time |
52h 29m (Margin: ~25%) |
|||||||
|
UST (Calc Getitback) |
Done |
27.10 |
28.11 |
Initial: 24-30h Approved: 36h |
W: 2h 46m T: 75h 55m |
Andrii (Getitback) |
Margin ~28% Approved new request – 6h |
|
|
Stingray |
Hold |
325h |
W: 0 |
Client is preparing the content |
||||
|
Saclab |
ON TRACK |
114h 7m |
Deployed to live new project “Buyer fee“ on 1.12 |
|||||
Leave a Reply