17. Support weekly report 27.11-03.12 (Andrii)

Project Schedule & Scope Status

Scope/Projects

Ticket

Status
Done In progress hold

Opened

Date of delivery

Estimation/Budget

Fact spent

Asgn

Comment

NUCC


NUCC-20

hold

20.11

21.11

Kjartan

I sent an investigation to the client

Total time

boa


BOA-93

Done

28.11

30.11

Danny Kurasinski

Bug, won’t be paid for this fix

Total time

2h 43m

Casa-Nobile


CN-134

In progress

20.11

Egzon Cekaj

related to other task with safepray


CN-133

Done

20.11

1h 0m

Egzon Cekaj

Tested new cert

Total time

1h 0m

Chiidaspa


CHIDA-56

Done

24.11

29.11

11h 9m

Danny Kurasinski

Problems with prices in the checkout


CHIDA-58

Done

26.11

01.12

4h 10m

Danny Kurasinski


CHIDA-57

hold

26.11

8-9h

32m

Danny Kurasinski

Wait approving estimation

Total time

16h 3m

COBAX


CBX-152

In progress

30.11

2h 1m

Liliano Tenore

couldn’t fix, wrote to plugin’s support


CBX-146

Done

14.11

27.11

45m

Liliano Tenore


CBX-144

In progress

9.11

Egzon Cekaj

changes in form functionality and SMTP


CBX-150

Done

27.11

30.11

45m

Egzon Cekaj


CBX-149

Done

17.11

27.11

8m

Egzon Cekaj


CBX-151

hold

28.11

3m

Liliano Tenore

wait info from Liliano, maybe task is not needed

Total time

3h 42m

FUJI


FUJI-88

In progress

28.11

~8h

6h 35m

Severin Bucher


FUJI-89

In progress

30.11

Severin Bucher

Total time

6h 35m

FWFO


FAIR-39

In progress

21.11

4m

Severin Bucher

complicated git flow on client side

Total time

4m

Gefra


GEF-22

In progress

16.11

6-8h

Severin Bucher

Approved estimation and can start

Total time:

Just.Swiss


JS-8

In progress

25.10

18-20h

Danny Kurasinski

wait approve estimation


JS-12

In progress

14.11

5-6h

3h 48m

Danny Kurasinski

need to fix anchor link

Total time:

3h 48m

Rosarot


ROS-24

In progress

20.11

19m

Egzon Cekaj

investigated showing all cases


ROS-25

In progress

27.11

3m

Egzon Cekaj

different design and current styles on a case page

Total time

22m

Flyttesiden


FLT-171

In progress

21.11

Mikael

We have to add some fields to edit texts on front-end part


FLT-170

In progress

21.11

Mikael

Changes on checkout steps


FLT-172

Done

28.11

29.11

22m

Total time

22m

Win4Win


W4W-112

In progress

28.11

3h 48m

Chiara Gragnano

have to fix mandatory birthday field on mobile

Total time

3h 48m

WSA


WSA-26

In progress

3.11

1h 16m

Danny Kurasinski


WSA-32

Done

28.11

29.11

1h 31m

Danny Kurasinski

Total time

2h 48m

Auto-Monkey


TL-129

Done

29.11

01.11

2h 7m

Luca Campanaro

Total time

2h 7m

Bluecare


BLUEC-559

Done

28.11

29.11

2h 19m

Severin Bucher

Total time

2h 19m

Kiana


OLKS-4

Done

28.11

29.11

1h 19m

Danny Kurasinski

Total time

1h 19m

PET


PET-21

In progress

28.11

2h 31m

Severin Bucher

have to fix on other languages

Total time

2h 31m

UST


UST-127

Done

31.10

29.11

3h

2h 58m

Kateryna Lytvinchova

Total time

2h 58m

Total support time

52h 29m (Margin: ~25%)

UST (Calc Getitback)

Done

27.10

28.11

Initial: 24-30h

Approved: 36h

W: 2h 46m

T: 75h 55m

Andrii (Getitback)

Margin ~28%

Approved new request – 6h

Stingray

Hold

325h
+23h (new requests)

W: 0
T: 514h 27m
Dev+QA: 474h 34m
PM: 40h 53m

Client is preparing the content

Saclab

ON TRACK

114h 7m

Deployed to live new project “Buyer fee“ on 1.12
We have in total for 3 months ~685h
For now (Oct-Dec) – 694h 31m

Comments