Weekly report 28.08-01.09

Project Schedule & Scope Status

Scope/Projects

Status

Deadline

Budget

Additional Requests

Team

Update

Estimated

Spent

Estimated

Spent

ROCKEN

ON TRACK

1316h
(August)

ROCKEN team

  • Ivan & Vika are testing Talent; Dasha continue working on BI board (charts connecting FE to BE); Anton’s completing additional requests for Companies (Job module, KT); Sasha is working on Activities module + bug fixing; Valya continue working on Talent Security & Contact form

One-Line: Porsche

ON TRACK
(support)

96h

77h

Laravel: Slavik Syvyniuk
Laravel Lead: Yurich
QA: Ilya Bilyk

  • Completed creating brochure process adjustments (had a few bugs to fix), waiting for approve to push it live and will work on next features scope

Rief Media: MBCA

PAUSED

396-516h

387h
(Total)

FE/BE: Tetiana Tkachuk
QA: Filipp Antonov

  • No updates

Comments

Leave a Reply