Weekly report 31.07-04.08

Project Schedule & Scope Status

Scope/Projects

Status

Deadline

Budget

Additional Requests

Team

Update

Estimated

Spent

Estimated

Spent

ROCKEN

ON TRACK

1671h
(July)

ROCKEN team

  • Completing Talent, plan to have a demo for Toni by the end of this week

  • Dasha continue working on BI board (this week start work with front-end and connect back-end); Anton completed Processes and Dima works on it from the Talent side (connecting FE + refactor), currently working on additional requests for Companies (Job module, KT); Sasha is working on Activities module for CRM + bug hunting

  • CRM features report will be done with Dima this week

One-Line: Porsche

ON TRACK
(support)

07.08.2023

96h

61h

Laravel: Slavik Syvyniuk
Laravel: Yurich

  • Completed creating brochure process adjustments, waiting for final approve for new features

Rief Media: MBCA

PAUSED

396-516h

387h
(Total)

FE/BE: Tetiana Tkachuk
QA: Filipp Antonov

  • No updates

General (other + PMO)

ON TRACK

  • Onboarding new PMs in progress

  • RiefMedia – assist Nastya in RiefMedia onboarding, and helping with the projects while Anna is on vacation

  • Flytte – had a call with Mikael and Andrii last week, discussed & prioritized his requests – Andrii is responsible for the project from now, need dev resources to complete the requests (candidate from Ivan part time – need info)

  • Support team – discussed workload for Olga & Andrii – Olga will be responsible for OneLine projects & Andrii will work with other clients

  • Support portal (JIRA Service Management) – Givi worked on automations last week and we reached a limit of the rule execution (there are 100 rules / month in the Free version), so I believe we need to upgrade it for the future (63$/month – Standard plan with 500 rule counts and 141$ – Premium 1000 rule counts)
    No need to upgrade it for now, since it be renewed from next month and for testing/implementation process it’s okay