Project Schedule & Scope Status
|
Scope/Projects
|
Status
|
Deadline
|
Budget
|
Additional Requests
|
Team
|
Update
|
|
|
|
|
Estimated
|
Spent
|
Estimated
|
Spent
|
|
|
|
ROCKEN
|
ON TRACK
|
–
|
–
|
1329h (July)
|
–
|
–
|
ROCKEN team
|
|
|
Flyttesiden
|
ON TRACK (support)
|
–
|
–
|
–
|
–
|
–
|
Lead: Oleh Honcharuk BE: Valera Boyko FE: Elvin Agaragimow QA: Filipp Antonov
|
|
|
One-Line: Porsche
|
ON TRACK (support)
|
07.08.2023
|
96h
|
43h
|
–
|
–
|
Laravel: Dima Sviridenko Laravel: Yurich
|
-
Slavik completed the adjustments of creating brochures process (very satisfied with his work), will give it to Danny & Egzon on Monday to check and gather their feedback
-
Brochure features (122h) waiting for approve
|
|
Rief Media: MBCA
|
PAUSED
|
–
|
396-516h
|
387h (Total)
|
–
|
–
|
FE/BE: Tetiana Tkachuk QA: Filipp Antonov
|
|
|
General (other)
|
ON TRACK
|
-
RiefMedia – divided projects between Anya and Nastya; will notify RiefMedia regarding our management changes this week (Nastya will be responsible for the particular projects, and I’ll be responsible for the delivery projects in general)
-
Projectrak – had a presentation last week, PM team is already notified that we should update status there, have few adjustments for the update process in Projectrak, plan to work with it this week and send the instructions for the whole team
-
Support portal (JIRA Service Management) – Givi worked on automations last week and we reached a limit of the rule execution (there are 100 rules / month in the Free version), so I believe we need to upgrade it for the future (63$/month – Standard plan with 500 rule counts and 141$ – Premium 1000 rule counts) No need to upgrade it for now, since it be renewed from next month and for testing/implementation process it’s okay
|