Project Schedule & Scope Status
|
Scope/Projects |
Status |
Deadline |
Budget |
Additional Requests |
Team |
Update |
||
|---|---|---|---|---|---|---|---|---|
|
Estimated |
Spent |
Estimated |
Spent |
|||||
|
Project 1 |
ON TRACK |
10.11.23 |
100h |
50h |
10h |
– |
||
|
Project 2 – Milestone 1 |
WITH RISK |
|||||||
|
Project 2 – Milestone 2 |
PAUSED |
|||||||