19.06. – 23.06 Weekly Project Report

(синяя звезда) Date

(синяя звезда) Participants

(синяя звезда) Discussion topics

Project

Status

ETA

Updates

Saclab US

In progress

28th of June

  • Running to the Finish line with the development. on Monday the 26th we are starting the testing by the customer

  • Left are Hubspot and giftcard – customer is aware of Hubspot. Giftcard will be done today. All bugs found by Fillip are fixed

  • Plan is still at hand to launch on the 28th

  • 4th of July starts a Marketing campaign

Saclab SnS

In progress

30th of June

  • On the Finishline

  • At the moment the deadline works as expected

  • Plan to show the demo tomorrow, Tuesday the 27th

Saclab General

In progress

  • Working on the assigned issues by @Thu (no sence to write them all down)

  • Had an issue with the server on Friday. Took a couple of hours to fix. Still not sure what was caused. We will make a research

Digitech

In progress

26.06

  • Oleksii (Unlicensed) Finalised the pages and all the bugs

  • Awaiting confirmation from the customer

  • Wrote the customer regarding billing on Saturday, awaiting for a reply

PMO

Task

Status

Updates

Support

In progress

PMO

In progress

  • Mostly 1:1s

  • Assisting with the estimations, especially big projects

  • Had an incoming potential estimation from Coreteka, already sent.

Meeting with sophiabilyk

Done

Meeting with Sophia 22.06.2023

Comments