8. Support weekly report 25.09-29.09 (Andrii)

Project Schedule & Scope Status

Scope/Projects

Ticket

Status

Opened

Date of delivery

Estimation/Budget

Fact spent

Asgn

Comment

Cobax


CBX-125

Done

28.09

4h 41m

Luca Campanaro

save contacts while user fill out the checkuot steps


CBX-129

Done

28.09

4h 48m

Update git for live


CBX-132

Done

28.09

34m

Luca Campanaro

Change text


CBX-115

Done

28.09

31m

Luca Campanaro

Add text at some checkout places


CBX-127

Done

28.09

6m

Luca Campanaro

Remove the chechbox for terms and condition


CBX-128

Done

28.09

3m

Luca Campanaro

Change the text, button


CBX-117

Done

28.09

2m

Luca Campanaro

Products area should be clickable


CBX-131

Done

28.09

2m

Luca Campanaro

fix the text view


CBX-133

Done

26.09

26.09

24m

Liliano Tenore

just install the plugin, waiting new task according to the google shop

Total time

11h 9m

Bluecare


BLUEC-553

Done

26.09

28.09

1.5-2h

1h 10m

Severin Bucher 

change styles


BLUEC-552


BLUEC-555

Done

26.09

29.09

2-2.5h

1h 57m

Severin Bucher 

change the logic for destination page after sending form


BLUEC-549

Done

29.09

27m

Severin Bucher 

add FR and IT languages for the form

Total time

3h 34m

Rosarot


ROS-21

Hold

14-19h

13m

Luca Manz

Need to add blog page, wait approving

Total time

13m

Boa


BOA-84

Done

29.09

4h 37m

Danny Kurasinski

Change the filters of first column and column years

Total time

4h 37m

Auto-Monkey


TL-120

In progress

27.09

2h 26m

Luca Campanaro

Auto send big amounts of lead with settings


TL-117

In progress

21.09

2h 12m

Luca Campanaro

Add new tab-service


TL-121

Done

27.09

27.09

1h 3m

Luca Campanaro

Add new tab-service


TL-119

22.09

25.09

8m

Luca Campanaro

Total time:

6h 1m

Stingray

In progress

325h
+23h (new requests)

449h 48m (total)
408h 55m (dev+qa)
40h 53m (pm)
1h 38m (last week)

The client escalated. A meeting was held with managers and supervisors from both parties. It was agreed to provide updated animation functionality by Wednesday (4.10), and tasks were approved as new requesters for 23 hours.