5. Weekly project report 29.01-04.02 (Andrii)

Project Schedule & Scope Status

Scope/Projects

Status

Deadline

Budjet

Editional requests

Team

Comment/Update

Estimated

Spent

Estimated

Spent

Saclab

ON TRACK

200h
(January)

196h
(January)

Dmitro Savchenko (WP)
Anna Aksonenko (WP)
Filip Antonov (QA)

Agreements: Jan-Mar 600h

Tracked:
Jan: 196h/200h
Week 1: 33h
Week 2: 56h
Week 3: 44h
Week 4: 38h
Week 5 (29.01-04.02): 34h

Dev: 140h (Margin ~45%)
QA: 38h (Margin ~57%)
DevOps: 16h (Margin ~78%)
PM: 0
Total margin Jan: ~44%

Comments