21. Weekly report 25.12-31.12 (Andrii)

Project Schedule & Scope Status

Scope/Projects

Ticket

Status
Done In progress hold

Opened

Date of delivery

Estimation/Budget

Fact spent

Asgn

Comment

NUCC


NUCC-20

In progress

20.11

Kjartan


NUCC-23

In progress

8.12

5-6h

Kjartan

Total time

Casa-Nobile


CN-135

hold

14.12

1h 17m

Luca Manz

wait plugin support

Total time

1h 17m

Chiidaspa


CHIDA-61

Done

7.12

17m

Egzon Cekaj

Total time

17m

PET


PET-24

Done

13.12

21.12

33m

Severin Bucher

Total time

33m

WSA


WSA-26

In progress

3.11

Danny Kurasinski
Luca Manz

Can deploy this week


WSA-35

Done

19.12

29.12

2h

1h 25m

Luca Manz

Ready on stage

Total time

1h 25m

Total support time

3h 32m (Margin: ~ -190%)

Saclab

Agreement IMS (Oct-Dec) – 310h + 40h (+11h in January)

Agreement 2024 (Jan-Mar) – 600h

October:
GENERAL – 187h
IMS – 98.5h
OTHERS – 10h
TOTAL – 295.5

November:
GENERAL – 181
IMS – 193.5
OTHERS – 0
TOTAL – 374.5

December:
GENERAL – 47
IMS – 282
OTHERS – 0
TOTAL – 329

TOTAL 4TH QUARTER:
GENERAL – 415
IMS – 574
OTHERS – 10h
TOTAL – 999 

Comments