13. Support weekly report 30.10-05.11 (Andrii)

Project Schedule & Scope Status

Scope/Projects

Ticket

Status
Done In progress hold

Opened

Date of delivery

Estimation/Budget

Fact spent

Asgn

Comment

Cobax


CBX-140

Hold

19.10

1h 20m

Luca Campanaro

Need to analyze with client possible implementations

Total time

1h 20m

FUJI


FUJI-85

Done

3.11

3.11

45m

Severin Bucher

fix layouts

Total time

45m

Flytte


FLT-169

Done

16.10

31.10

2h

Mikael

Fix the emails sendings and prepare the email with list of orders to print


FLT-168

In progress

6.10

1h

Mikael

Solve the problem with duplication orders in stripe


FLT-167

Done

6.10

31.10

1h

Mikael

implement strex keys

Total time

4h

FWFO


FAIR-38

Done

19.10

1.11

1h 39m

Severin Bucher

prepare temporary main page, work with devops on client side, very difficult CI/CD flow

Total time

1h 39m

Boa


BOA-88

Hold

18.10

17m

Danny Kurasinski

Done on stage, wait review

Total time

17m

Auto-Monkey


TL-127

Done

27.10

30.10

6-8h

4h 49m

Luca Campanaro

prepare settings page for autosending letters


TL-128

Done

3.11

3.11

24m

Luca Campanaro

investigate issue about 4th emails

Total time

5h 13m

Casa-Nobile


CN-131

Done

23.10

3.11

3.5-4.5

3h 34m

Luca Manz

fix the problem that shows dashboard panel


CN-126

Hold

06.10

45m

Luca Manz

investigation of the plugin that creates the lables and bar codes

Total time:

4h 18m

NUCC


NUCC-18

Done

24.10

3.11

3-4h

2h 56m

Kjartan

investigate and solve hosting’s security suggestions

Total time:

2h 57m

Just.Swiss


JS-11

Done

2.11

3.11

1h 2m

fix the stage on one line side, to show some tasks for clients


JS-8

Hold

25.10

32-38h

35m

Danny Kurasinski

sent estimation with suggestions

Total time:

1h 36m

Win4Win


W4W-94

Done

23.10

31.10

7-8h

7h 21m

Chiara Gragnano

new type of contests


W4W-96

Done

30.10

30.10

1h 32m

Chiara Gragnano

fix mobile mobile version, long loading some page


W4W-99

Done

3.11

3.11

2h 11m

Egzon Cekaj

prepare list of contacts for 100 cities


W4W-98

Done

3.11

3.11

1h

Danny Kurasinski

investigate how to do it from the admin panel (content on French side)


W4W-97

Done

30.10

3.11

42m

Chiara Gragnano

change loyout

Total time

12h 46m

WSA


WSA-22

Done

25.10

1.11

3.5-4.5

2h 58m

Luca Manz

Solve isses with spam, implement SPF and DKIM

Total time

2h 58m

Chiidaspa


CHIDA-53

Done

31.10

31.10

15m

Danny Kurasinski

There was a problem with cache on main page


CHIDA-54

Done

2.11

2.11

2h 18m

Danny Kurasinski

Can’t finish booking because of error with code on finish step

Total time

2h 33m

UST (Calc Getitback)


UST-122

In progress

27.10

8-10h

5h 48m

Andrii (Getitback)

Almost finish Back end part


UST-123

In progress

27.10

8-10h

4h 14m

Andrii (Getitback)

Almost finish Back end part


UST-126

Done

27.10

2.11

4-5h

5h 30m

Andrii (Getitback)

Finished Front-End part

Total time

15h 32m

Total support time

51h 54m

Stingray

Hold

325h
+23h (new requests)

511h 37m (total)
470h 44m (dev+qa)
40h 53m (pm)
1h 59m (last week)

On Friday evening had some questions regarding fill out the content.

Before go to the live we have to implement and add several versions of languages.