Date
–
Participants
Discussion topics
|
Project
|
Status
|
ETA
|
Updates
|
|
Saclab US
|
Done
|
|
|
|
Saclab SnS
|
Done
|
|
|
|
Saclab General
|
In progress
|
|
|
|
Saclab IMS
|
In progress
|
|
-
Started a new project with Saclab, Integration with Airtable
-
Finish dates are 4-11th of December
-
So far going great, Anna is on time.
-
Sending recorded videos of the integration on weekly basis
|
|
Performance Frontiers
|
In progress
|
|
|
HOBG
|
Task
|
Status
|
Updates
|
|
Growth
|
In progress
|
-
Started the new position in the company as Head of Business Growth
-
Discussed with alex.l@cheitgroup.com the plans and responsibilities
-
Finilasied with the Maintanance services in regards to the content, prices and design:
-
Contracts are in progress of creation and first draft will be provided this week
-
Had many calls with Marina`s Leads – 4 projects came in
|