Date
–
Participants
Discussion topics
|
Project
|
Status
|
ETA
|
Updates
|
|
Saclab US
|
In progress
|
30th of June
|
-
Running to the Finish line with the development
-
Plan to start testing from the 6th of June (I was off 2.5 days, so need to catch up on all stats in order to start the testing)
-
Worked on the weglot plugin in order for correct translation
-
Plans for the week are
-
gift cards price in USD
-
emails and invoices in USD
-
Add/change the checkout process in order to fulfil the the US version requirements (no returns policy, taxes included, etc
-
Hubspot price in USD
-
Plan to check all the logged time, and issue the report and bill
|
|
Saclab SnS
|
In progress
|
30th of June
|
-
Worked on the hubspot side by creating new columns and fields
-
Rewrote the code of the sell your bag functionality in order to make it more cleaner and more correct
-
Plan is to get as much questions as possible from Honcharuk Oleh this week and get the answers with Thu
-
At the moment the deadline works as expected
-
In the 20th dates of June plan to add a Frontend developer for a couple of days
-
Do not see in my Timedoctor account hours of Honcharuk Oleh Plan is to work on it on the 5th of June
|
|
Saclab General
|
In progress
|
|
-
Finally fixed the A/B testing issue
-
Fixed the A/B on the developer level, now it is showing correct positions of the upsale in the checkout
-
Set up from scratch analytics based on the requirements
-
Working on new tasks and fixes on a daily basis
-
Plan to have the dedicated QA start testing the US version. If testing will require more hours, plan to add one more QA
|
|
Digitech
|
In progress
|
09.06
|
-
Oleksii (Unlicensed) is working on the final pages, plan to finalise them at the beginning of the week. Probably tomorrow
-
Work on the final bugs until End of the week
-
Bill the customer based on the logged hours. But first, he would run the testing
-
Discuss with management if we are going to offer maintanence and support for the project
|
PMO
|
Task
|
Status
|
Updates
|
|
Support
|
In progress
|
|
|
Trainings
|
In discussion
|
|
|
PMO
|
In progress
|
-
Acknowledged feedback from Management team
-
Plan to write it down in Confluence and start tracking improvements
-
Starting this week will be using the 1:1 templates, based on which personal growth for each PM will be created
-
Plan to create a personal workload based on activities
|