26.06. – 02.07 Weekly Project Report

(синяя звезда) Date

(синяя звезда) Participants

(синяя звезда) Discussion topics

Project

Status

ETA

Updates

Saclab US

In progress

03.07

  • Had bugs, that influenced on the release on the 28th of June

  • Worked hard all week and weekend to make it on time, for the third of July

  • Still working on the improvements, more likely will launch on the third

Saclab SnS

In progress

05.07

  • 99% of the project finished

  • At the moment the deadline works as expected

  • Demo was not yet shown, since the customer asked to focus on the US version.

  • Plan to show more likely on the 5th of July

  • Waiting for Honcharuk Oleh to track the hours so I can generate the report and send the hours report to the customer for the whole Saclab project

Saclab General

In progress

  • Working on the assigned issues by @Thu (no sence to write them all down)

  • Researched the issue with the server. Plan to estimate how to fix the issue, and let the customer know. But only after the 4th of July

Digitech

In progress

26.06

  • Project finalised

  • Waiting from Alina an invoice for 70 hours (I asked at first 90. he asked 60, we came down to 70 hours to charge, which is totally great)

PMO

Task

Status

Updates

Support

In progress

PMO

In progress

  • Did not have mostly 1:1 this week, as focus was on the launch of Saclab

  • Working on the estimation for the mobile app, need to have a call with alex.l@cheitgroup.com

  • Sent an estimate to Coreteka regarding the wordpress project

  • Hired two Project managers and one Support manager

Comments