23.01.2023 – 27.01.2023

(синяя звезда) Date

(синяя звезда) Participants

(синяя звезда) Goals

(синяя звезда) Discussion topics

Task

Status

Updates

All projects document

Done/ awaiting information

Document ready, however some information is still awaited to be provided

All developers document

Done/ awaiting information

Document ready, however some information is still awaited to be provided

Daily tasks

Always in progress

Took part in estimation, call with the potential customer, organisation of meetings with Coreteka, daily communication with the team

Confirmed flows

Done

Had an offline meeting with Sophia Bilyk (Unlicensed) regarding the flows and potential next steps

CV site

In progress

This week, we will provide the customer up to 2 templates out of three he has provided. Panchenko is working on those.

Checklist implementation

In progress

Created a draft for now, will also discuss with Sophia Bilyk (Unlicensed)

Project handover checklist

We will have a call tomorrow regarding the documentation, so will discuss it also with her.

KPI implementation

TBD

Plan to start working on it next week. Since alex.l@cheitgroup.com will be in Lviv, it will be a great point of discussing this topic offline

Oneline GA

In progress

On the 30.01 a call is planned with Liliano from oneline, in order to discuss the issue he reported regarding GA, that it takes a lot of time and is not working as expected.

1:1

In progress always

Had 1:1 with Ruslan, Anna and Sophia.

With Ruslan we discussed his new project Stingray, along with the planning of the tasks into sprints, new flow that we are testing along with code review. So far great working on it.

With Anna we discussed the new potential project, estimation. Basically Anna checks with me within the week if any kind of suggestions are needed.

Did not have the opportunity to speak with Kate, since she has a release coming up. Hopefully will do it this week.

Code Review

In progress

Spoke today with Honcharuk Oleh – process is in testing. On tomorrow`s call 31.01 we will get the latest updates regarding it.

Sprint building

In progress/ Done

Basically on the new stingray project all the tasks and subtasks were devided into sprints, however only the first sprint is shown in the backlog, other sprints are empty. Such is because the status of the tasks in the other sprints shows backlog. If change to open, it will be shown in the open tasks of the current sprint and as planned tasks in the next ones. Checking on what is the issue here, will discuss it with Ira on the call tomorrow

Due dates

TBD

As I see, there are some projects that have such field option, but most do not. I am checking also into this, maybe the field configuration is to be changed. If wont find the issue myself, will also discuss it with Ira on the call tomorrow.

(синяя звезда) Action items

  •  