Saclab US

In progress

  • In progress of bugs fixing. This is the only focus

  • Also had a call with the customer regarding the US version and the reports. Plan to make a research and deduct all the hours that are on the side of CHEIT

Saclab SnS

In progress

  • In progress of bugs fixing. Basically the only priority

  • Also Intense testing.

  • Since Honcharuk Oleh is on vacation, the week of 17.07-21.07 we were testing the whole project. Not all yet tested

  • Plan to go online this week with the project

  • Customer is testing as well, however not a lot of bugs

Saclab General

In progress

  • Working on the assigned issues by @Thu (no sence to write them all down)

  • Fixed the main issue with the server. Rewrote the cron. At the moment all is working good.

  • Still in progress of testing the server. Fall down almost every early morning for a couple of minutes

  • Had a call with the customer in regards the Future of Saclab, need to review the code and provide an estimate for refactoring

  • Also in plan to implement IMS until the end of the year

Digitech

Done

  • Project finalised

  • Waiting for the paid invoice

  • A couple of more bugs have come in and Oleksii (Unlicensed) has fixed them

  • The customer is not yet responding. Pinged him once again

PMO

Task

Status

Updates

Support

In progress

PMO

In progress

  • Did not have 1:1 this week, as focus was on the launch of Saclab

  • Working on the estimation for the mobile app, need to have a call with alex.l@cheitgroup.com

  • Sent an estimate to Coreteka regarding the wordpress project

  • Hired two Project managers and one Support manager