Project Schedule & Scope Status
|
Task/Ticket |
Status |
Opened |
Date of delivery |
Estimation |
Fact spent |
Comment |
|
|---|---|---|---|---|---|---|---|
|
1 |
|
Done |
02.08 |
15.08 |
14h 19m |
Add to checkout steps information about prices of services (flyttesiden) |
|
|
2 |
|
Done |
02.08 |
17.08 |
3h 41m |
Add to checkout steps information about prices of services (flytteskjema) |
|
|
3 |
|
Done |
02.08 |
21.08 |
6h 7m |
Tasks for optimization site: |
|
|
4 |
|
Done |
02.08 |
21.08 |
10h 6m |
Change status for post signs in personal user account, switch to sendt in 10 days after reconfirmation date (flyttesiden) |
|
|
5 |
|
Done |
02.08 |
24.08 |
3h 10m |
Change status for post signs in personal user account, switch to sendt in 10 days after reconfirmation date (flytteskjema) |
|
|
6 |
|
Done |
02.08 |
15.08 |
8h 3m |
Add styles for Region post code on registration form, REFACTORING |
|
|
7 |
|
Done |
22.08 |
22.08 |
1h |
Work with smtp issues, apply new credentians |
|
|
8 |
|
Hold |
02.08 |
– |
45-86h |
13h 53m |
prepare visual design, technical documentation for developers, estimation |
|
9 |
|
Hold |
53m |
||||
|
10 |
Task discussins, review and communications |
10h 2m |
|||||
|
Total |
71h 14m |