Project Schedule & Scope Status
|
Scope/Projects |
Status |
Initial ETA |
Current ETA |
Initial Budget |
Current Budget |
Team |
Update |
|---|---|---|---|---|---|---|---|
|
ROCKEN |
ON TRACK |
– |
– |
– |
1587h |
ROCKEN team |
|
|
Flyttesiden |
ON TRACK |
– |
– |
– |
4h |
Oleh Honcharuk |
|
|
Rief Media: MBCA |
ON TRACK |
Dec 2022 |
– |
396-516h |
387h – overall |
Tetiana Tkachuk |
|
|
Rief Media: S&Sinc. |
PAUSED |
– |
– |
– |
15h |
Dima Nagaev |
|
|
Rief Media: Avanti |
ON TRACK |
– |
14.04 |
– |
178h |
Dmytro Melnyk |
|
|
Rief Media: Futures Financial |
ON TRACK |
06.04 |
06.04 |
– |
10h |
Dmytro Rogkov |
|
|
Rief Media: McDonald |
ON TRACK |
– |
07.04 |
– |
10h |
Dmytro Melnyk |
|
|
Rief Media: New Project’s Requests |
ON TRACK |
– |
– |
450-700h |
– |
– |
|
|
OneLine: Porsche |
ON TRACK |
– |
– |
– |
1,5h |
Dima Sviridenko |
|
Implementation report (20.03-24.03)
|
Task |
Status |
ETA |
Update |
|---|---|---|---|
|
Jira administration |
IN PROGRESS |
– |
|
|
Time tracking integration + Jira features & automation |
IN PROGRESS |
– |
|
|
Projectrak set up |
IN PROGRESS |
– |
|
|
Support process |
IN PROGRESS |
– |
|
|
Communication training for Olya |
COMPLETED |
– |
|
|
Documentations & Procedures |
IN PROGRESS |
– |
|
|
Jira Integrations / add-ons |
IN PROGRESS |
– |
|