Weekly report 21.08-25.08

Project Schedule & Scope Status

Scope/Projects

Status

Deadline

Budget

Additional Requests

Team

Update

Estimated

Spent

Estimated

Spent

ROCKEN

ON TRACK

1037h
(August)

ROCKEN team

  • Dima completed Talent last week and we already started with internal QA; Dasha continue working on BI board (charts connecting FE to BE); Anton’s working on additional requests for Companies (Job module, KT) + Activities module; Valya continue working on Vacancy & Profile module

  • In general, we almost finished with the backend part (CRM+Talent / BI board), many modules and elements just need to be connected on the front-end side and refactored, so Sasha will be also involved to FE part connecting

One-Line: Porsche

ON TRACK
(support)

96h

77h

Laravel: Slavik Syvyniuk
Laravel Lead: Yurich
QA: Ilya Bilyk

  • Completed creating brochure process adjustments (had a few bugs to fix), waiting for approve to push it live and will work on next features scope

Rief Media: MBCA

PAUSED

396-516h

387h
(Total)

FE/BE: Tetiana Tkachuk
QA: Filipp Antonov

  • No updates