Weekly report 03.04-07.04

Project Schedule & Scope Status

Scope/Projects

Status

Initial ETA

Current ETA

Initial Budget

Current Budget

Team

Update

ROCKEN

ON TRACK

348h
(April)

ROCKEN team

  • Working mostly on new system + support requests

  • Animation – in progress, working with design team to make it more dynamic (as Toni wished)

  • Сall w/ Toni went OK as always, he expects ready for UAT architecture in 2 month, then we would have internal QA + ROCKEN UAT phase

Rief Media: MBCA

ON TRACK
(redesign)

Dec 2022

396-516h

387h
(Total)

Tetiana Tkachuk
Filipp Antonov

  • Had a call with Brent and TrueDigital – agency, which would help MBCA to finalize the portal and would work collaboratively with them in the future
    TrueDigital would be responsible for gathering final content, checking portal to ensure we’re ready to go-live, give their recommendations what can be improved

Rief Media: Avanti

ON TRACK

182h
(Total)

Dmytro Melnyk
Dmitriy Nagaev
Filipp Antonov

  • Received few additional requests, worked on it last week and plan to finish it on Monday

  • Waiting for 1 more page

Rief Media: McDonald

ON TRACK

47h
(Total)

Dmytro Melnyk
Artem Simonchuk
Filipp Antonov

  • Finishing last preparations of the Home page and plan to send for review on Monday

  • Waiting for more pages soon
    No deadline on dev for pages (trying to turn 2 pages a week if possible, when we receive the design)

Rief Media: Futures Financial

ON TRACK

40h
(Total)

Dmytro Rogkov
Dmitriy Nagaev
Filipp Antonov

  • Completed the page, waiting for client’s review

Rief Media: Girard Bengali

ON TRACK

27h
(Total)

Ihor Havrilenko
Artem Simonchuk
Filipp Antonov

  • Completing Case Wins QA, plan to send for review on Monday

Rief Media: S&Sinc.

PAUSED

71h
(Total)

Dima Nagaev
Oleksii Reshetnyk
Filipp Antonov

  • Transferred changes live, had 1 small request last week

Rief Media: New Project’s Requests

ON TRACK

450-700h

  • Argon – 19.04 should receive Home page for development

  • MYCON – 10.04 Home page for development

  • Music & Media – HP initial 10.04
    The amount of work is getting bigger and more requests are coming, I would check the situation with our workload at the moment when they send ready-to-dev designs; most probably will add Anna (PM) to help me with project managing

OneLine: Porsche

ON TRACK
(support)

0.5h

Dima Sviridenko

  • Would have call w/ Egzon, Danny 11.04 – apparently they want to propose new features to Porsche (becomes interesting (синяя звезда) )
    I would estimate discussed features with Dima Sviridenko and most probably would involve Vitaliy Volchenko for the development

Flyttesiden

ON TRACK
(support)

0.5h
(April)

Oleh Honcharuk
Elvin Agaragimow
Filipp Antonov

  • Would assign the project to Olya, also would try to onboard Valera this week as a support dev

  • Waiting for approve of the Vipps account to set it up live

Implementation report (03.04-07.04)

Task

Status

ETA

Update

Support process

IN PROGRESS

  • Would need to ping Ira regarding the progress status

Training for Olya / Mentoring

IN PROGRESS

  • Discussed current status of Olya’s projects, communication cases

  • Went through Jira tasks and trained her how to create new tasks

  • Discussed QA flow – Artem would work on support project’s QA and would be included to all support requests estimates

Jira Integrations / add-ons

IN PROGRESS

  • Plan to work with EazyBI after vacation

QA Dividing resources

COMPLETED

  • Since we have new QA, me & Ivan discussed dividing QA resources by projects & PMs – prepared the list of all current projects
    From now Artem is responsible for Support projects with Olya, and for Anya’s new projects, also Vika onboards him on current Anya’s projects – in approx. 2 months we want to have Vika full-time on Rocken
    Filipp is staying with Katya & me

Comments